Skip to Main Content
ContactSearchGift Certificates

2026 Cape Seal Project

What is Cape Seal?

Cape sealing is a two-step pavement preservation process that combines two roadway surface treatments. The process is designed to extend the life of the roadway by approximately 7 to 10 years, and is part of a cost-effective maintenance strategy to improve streets without a full reconstruction.

What to Expect

Businesses and visitors should expect limited traffic and temporary impacts to access during the work. The contractor will work to complete each street segment as quickly as possible. All dates and times are tentative and subject to change based on weather and construction conditions. A third application, to paint traffic and pedestrian markings, will occur later this fall.

Businesses with on-street/platform seating are reminded that structures must be removed by the end of the day Monday, September 7th and remain off the street until after pavement marking is completed later this fall (date tentative).    

The work will be completed in two phases. Dates are weather-dependent and subject to change.

Wednesday, September 9
Cass Street – Full Closure
North Cass Street Bridge to Washington Street & South Cass Street Bridge to 8th Street

 Thursday, September 10
Front Street – Partial Closure
Pine Street to Boardman Avenue

Hall Street – Flagging Operations to maintain traffic
W. Front Street to Grandview Parkway

Friday, September 11
Union Street – Partial Closure
Garland Street to South Union Street Bridge & 8th Street to 9th Street

8th Street – Flagging operations to maintain traffic
Union Street to Lake Avenue

Friday, September 11
Union Street – Partial Closure
Garland Street to South Union Street Bridge & 8th Street to 9th Street

Break (Streets will remain open)

 

 

PHASE TWO (dates subject to change)

Tuesday, September 15
Cass Street – Full Closure
North Cass Street Bridge to Washington Street &South Cass Street Bridge to 8th Street

 Wednesday, September 16
Front Street – Partial Closure
Pine Street to Boardman Avenue

Hall Street – Flagging operations to maintain traffic
W. Front Street to Grandview Parkway

Thursday, September 17
Union Street – Partial Closure
Garland Street to South Union Street Bridge & 8th Street to 9th Street

8th Street – Flagging operations to maintain traffic
Union Street to Lake Avenue